DAYS
: :
Until Evolution Genesis Release
Learn more
January 2, 2018 12:00 am

Project Portfolio Report

Dear All,

Please find the last portfolio report from the past year attached below (please accept my apologies for a delayed publishing). Summary comments:

  • Dash Core wallet 0.12.2.2 version released
  • Public beta release of Copay wallet preparations in progress
  • 5 new team members hired
  • Solid progress done with DAPI, Frontend and Copay projects
  • Scrum trainings for DAPI team provided and SCRUM sprints initiated in the team
  • Review and reorganisation of internal DIPs initiated by Quantum Explorer and Nathan Marley.
    Having this opportunity, let me wish all of us happy and prosperous New Year 2018!

https://www.dash.org/forum/attachments/2017-12-20-project-portfolio-report-pdf.5747/

Author: Robert Wiecko
Original link: https://www.dash.org/forum/threads/project-portfolio-report.17424/#post-159689


About the author


dash